Project Overview
BWWA became Australia’s first greenfield public airport to be built in 48 years when it opened in November 2014. The opening also marked a world first – the largest modern geopolymer concrete project containing absolutely NO Portland cement.
Wagners “Earth Friendly Concrete” (EFC) was used for the construction of all heavy duty pavements in the aircraft turning areas as well as a range of other building and civil works on the project. Using EFC instead of conventional concrete reduced CO₂ emissions by 6,600 tonne across the project. The aerial image shows the completed pavement works. The EFC turning node pavement is located at the Northern end of the runway and the EFC apron pavement is located on the Western side of the runway in front of the terminal and carpark.
The EFC heavy duty aircraft pavements were constructed using a slip form paver machine during the 2nd half of 2014.